helpIcon

How can we help?

sea-vessel

Cargo & Logistics / Economic Zones

Request for Building Permit

Pattern
Pattern

Request for Building Permit

Through this service, a Building Permit can be obtained through the Municipality E-permitting System (MEPS) prior to construction.

icon-phone
Phone
iconface-to-face
Face-to-Face
icon-app
Mobile App
icon-mail
Email
icon-website
Website
icon-mail
Others

Steps to Follow

STEP01

Project Registration on MEPs by the Consultant (Applicant). The requirements upon registration are Affection Plan, Lease agreement/ Power of Attorney for Tenant representative, approved DCR if any, Appointment letter from the Client & Consultant assignment letter. The last two documents are a standard form that can be downloaded from the system which must be completed, signed and stamped.

STEP02

Step 2

Obtain Site Clearance. The Affection Plan will be verified by all related entities for Approval.

STEP03

Step 3

Preparatory Approval. To secure the mandatory & pre-requisite approvals. This procedure can be done in parallel with step 2. Under DPA (Detailed Planning Approval) which is a pre-requisite, Transportation Approval and Planning for Estidama (where applicable) must be part of the package approval. ADCD, EAD, LDN, & Soil Investigation must be independently applied for approval. Any Entities that are not applicable for the project must submit a waiver.

STEP04

Step 4

Building Permit Approval. Once the Approvals have been obtained from all relevant entities and disciplines they will be filtered and reviewed by the Approval Review Control -Architectural, Structural, ADCD, ADDC. This to determine that the plans satisfy all code requirements and layout and building information align with each other.

STEP05

Step 5

Design Consultant to assign the Supervision Consultant and Contractor to prepare the necessary requirements for Pre-Construction and Construction stage.

STEP06

Step 6

Issuance of Building Permit. QR coded Building Permit and drawing layouts will be obtained after payment completion.

    6

    6

    6

    STEPS

Required Documents

Affection Plan

Lease agreement/ Power of Attorney for Tenant representative

Appointment letter from the Client & Consultant assignment letter.

DPA

Mandatory and Pre-requisite approval documents from external entities and relevant Authorities

Drawings and supporting documents and calculations

Required Documents

Affection Plan

Lease agreement/ Power of Attorney for Tenant representative

Appointment letter from the Client & Consultant assignment letter.

DPA

Mandatory and Pre-requisite approval documents from external entities and relevant Authorities

Drawings and supporting documents and calculations

Additional Information

Service ChargesNot Applicable 
Customer TypesBusinesses: AD Ports Investors
The Number of Visits Required0
Number of Interactions to Obtain the Service6
Service OutputBuilding Permit
Link to Other Services Within the EntityYes
Link to Other Services With External Government EntityYes

Charges List

N/A